Andover officials are weighing how to pay for improvements to the town’s high school, with scenarios ranging from limited upgrades costing $15 million to $18 million to a future replacement building costing hundreds of millions.

The estimates reflect different scopes and schedules, rather than competing prices for the same project. None is an adopted construction budget.

At its March 4 meeting, the Finance Committee reviewed three interim improvement options. Those ranged from limited facility upgrades to an approximately $80 million renovation with a new science wing.

The presentation estimated annual tax impacts of about $96 to $502 for those options. The minutes do not specify the property valuation or financing assumptions behind those figures, so they should not be read as estimates for every household.

Longer-term scenarios examined a new high school pursued through the Massachusetts School Building Authority. Estimated costs ranged from approximately $638 million for a 2027 application to more than $1.06 billion if the application were delayed until 2040.

Combining interim improvements with a later replacement would create overlapping debt and higher peak tax impacts, according to the presentation. The retirement of existing school-related debt would provide some offset.

A separate discussion at the committee’s Aug. 19 meeting identified $485 million as the starting assumption for financial analysis, with escalation costs to be incorporated. The minutes do not explain how that baseline relates to March’s $638 million scenario.

Town Manager Andrew Flanagan said the analysis would consider maintaining the existing school and pursuing improvements with or without MSBA funding. A full renovation would also be explored.

MSBA’s Core Program supports new construction, additions and major renovations. Its separate Accelerated Repair Program addresses more limited building improvements.

The town’s 2026–2027 strategic goals called for a financing report by Nov. 1 outlining viable options for new construction or major renovation. The town’s project page also identifies that deadline, but the records reviewed do not establish whether the report was delivered.

The School Committee’s AHS Finance Subcommittee is scheduled to meet Monday, Nov. 30, at noon in Conference Room A at the School Administration Building, 30 Whittier Court. Its posted agenda lists financials and approval of subcommittee minutes.